Question/Dilemma about High Bridge Construction...?
NW Mailing List
nw-mailing-list at nwhs.org
Wed May 7 10:43:00 EDT 2014
Bob:
There's one other fact that may confirm that the main
track was shifted from the center of High Bridge.
A quarter mile (or so) west of the Farmville-end of the
bridge, there was an 0.28 degree curve to the left
followed by an 0.28 degree curve to the right. Curve
had a 1" superelevation. The M/W Engineering Dept.
called it a "correction". Possibly this "correction"
placed the main track back to its original alignment.
Harry Bundy
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://six.pairlist.net/pipermail/nw-mailing-list/attachments/20140507/d2571ffc/attachment.html>
More information about the NW-Mailing-List
mailing list